ICT Strategy Work Task F


High Level Goals and Objectives Manage work of the ICT Consultant
Expected Results and Benefits Ensure work of consultant is compatible with rest of ICTS Programme. Ensure consultant delivers on-time and relevant information
Timing Starts Immediately. Consultant to be appointed by 30 September 2005. Requirements documents to be reviewed and approved by 8 February 2006
Prime Responsibility Management of ICT Consultants and their interface with the ICT Strategy Programme
Major Dependencies None from other WTs. Output needed to feed into WTJ
Risks and Potential Obstacles Suitable Consultant not identified, requirements not agreed on time
Description and Status WT-F-COVER
Documents ECE Development and Consultants' papers(requires Oxford username login, like Webmail or Weblearn)
Meeting 1 (19.01.06): Agenda Web
Membership Paul Jeffreys; Andrew Hynes, Lou Burnard, Bridget Lewis, David Rischmiller, Jim Davies, Mark Clark, Mark Round, Niall Hedderley