| High Level Goals and Objectives | Manage work of the ICT Consultant |
| Expected Results and Benefits | Ensure work of consultant is compatible with rest of ICTS Programme. Ensure consultant delivers on-time and relevant information |
| Timing | Starts Immediately. Consultant to be appointed by 30 September 2005. Requirements documents to be reviewed and approved by 8 February 2006 |
| Prime Responsibility | Management of ICT Consultants and their interface with the ICT Strategy Programme |
| Major Dependencies | None from other WTs. Output needed to feed into WTJ |
| Risks and Potential Obstacles | Suitable Consultant not identified, requirements not agreed on time |
| Description and Status | WT-F-COVER |
| Documents | ECE Development and Consultants' papers(requires Oxford username login, like Webmail or Weblearn) Meeting 1 (19.01.06): Agenda Web |
| Membership | Paul Jeffreys; Andrew Hynes, Lou Burnard, Bridget Lewis, David Rischmiller, Jim Davies, Mark Clark, Mark Round, Niall Hedderley |